June 22, 2018

The Ministry of Education has directed the contractor working on the E-Block project at Damanko in the Nkwanta North District to complete outstanding works before the commencement of the 2018/2019 academic year.

Sector Minister Dr. Mathew Opoku Prempeh made this known on the floor of the House, when answering a question from John Kwabena Bless Oti, as to when works will resume on the community Day Senior High School in Damanko.

He further told the House that, the “E-Block” project in the Volta Region is part of the 101 number of community SHS, which falls within the first phase being funded by Government of Ghana through the GETFund.

“Mr. Speaker the contractor has carried out seventy-two percent (72%) of work on the project and it was awarded to Messrs Westfalia Company Limited in August 2015 and the contract sum is GHc 6,546, 921.98, he said.

By: Kwaku Sakyi-Danso/ghanamps.com